Postal Service shares fleet replacement plans

Total investment expected to reach $9.6 billion

The United States Postal Service (USPS) announced that it plans to acquire at least 66,000 battery electric delivery vehicles as part of its 106,000 vehicle acquisition plan for deliveries between now and 2028. The vehicles purchased as part of this anticipated plan will begin to replace the Postal Service’s delivery fleet of over 220,000 vehicles.

Oshkosh postal truck Oshkosh Defense will build the Next Generation Delivery Vehicle for the U.S. Postal Service. (Illustration: USPS)

“We have a statutory requirement to deliver mail and packages to 163 million addresses six days per week and to cover our costs in doing so – that is our mission,” said Postmaster General Louis DeJoy. “As I have said in the past, if we can achieve those objectives in a more environmentally responsible way, we will do so.”

The Postal Service anticipates at least 60,000 Next Generation Delivery Vehicles (NGDV), of which at least 75% (45,000) will be battery electric. As part of this plan, a total of 21,000 additional commercial off-the-shelf (COTS) vehicles are also expected to be battery electric, depending on market availability and operational feasibility.

The Postal Service said it anticipates including internal combustion vehicles necessary to meet immediate vehicle replacement needs.

For any COTS vehicles purchased, the Postal Service will include a preference for domestic manufacturing.

Total investment expected to reach $9.6 billion including $3 billion from Inflation Reduction Act funds.

The announcement was enabled by the Postal Service’s overall network modernization efforts which allows for a more rapid deployment of EVs, and what it said was its improving financial condition which included the IRA funding.

The Postal Service said it will continue to evaluate and procure vehicles over shorter time periods to be more responsive to its evolving operational strategy, technology improvements, and changing market conditions, including the expected increased availability of battery electric vehicle (BEV) options in the future.

“The $3 billion provided by Congress has significantly reduced the risk associated with accelerating the implementation of a nationwide infrastructure necessary to electrify our delivery fleet,” said DeJoy. “While most of the electric vehicle funding will continue to come from Postal Service revenues, we are grateful for the confidence that Congress and the administration have placed in us to build and acquire what has the potential to become the largest electric vehicle fleet in the nation.”

“What is less widely understood is that our network modernization initiative is necessary to enable this vehicle electrification and will also provide meaningful cost and carbon reductions in other ways. A key focus of our modernization effort is to reduce inefficient transportation and improve distribution operations, resulting in far less air cargo and far fewer truck trips. When combined with our substantial commitment to the electrification of our delivery vehicles, the Postal Service will be at the forefront of our nation’s green initiatives.”

Ongoing commitment

The Postal Service said it is steadfastly committed to the fiscally responsible and mission capable roll-out of electric-powered vehicles for America’s largest and oldest federal fleet. The agency has continually assessed its capacity, financial position and vehicle mix over the past year:

  • February 2022: USPS completed its obligations under the National Environmental Policy Act process and issued a Record of Decision to acquire up to 165,000 NGDV, with a commitment for at least 10% BEV. This decision was expressly designed to provide the Postal Service the flexibility to acquire significantly more BEV NGDV should financial and operational circumstances permit.
  • March 2022: USPS announced a purchase order of 50,000 NGDV from Oshkosh Defense, including 20% BEVs.
  • July 2022: USPS announced its intent to conduct a Supplemental Environmental Impact Statement (EIS) that anticipated increasing the NGDV minimum BEV percentage to at least 50% and supplementing the NGDV order with a purchase of 34,500 COTS, so that the combined purchase would be for at least 40% BEV.
  • By May 2023: USPS will publish for public notice and comment a Draft Supplemental EIS that will assess the potential environmental impacts of vehicle purchase alternatives.

New NGDVs are expected to start servicing postal routes in late 2023.

STAY CONNECTED



Receive the information you need when you need it through our world-leading magazines, newsletters and daily briefings.

Sign up

POWER SOURCING GUIDE

The trusted reference and buyer’s guide for 83 years

The original “desktop search engine,” guiding nearly 10,000 users in more than 90 countries it is the primary reference for specifications and details on all the components that go into engine systems.

Visit Now

CONNECT WITH THE TEAM
Becky Schultz Vice President of Content Tel: +1 480 408 9774 E-mail: [email protected]
Julian Buckley Editor Tel: +44 (0) 1892 784088 E-mail: [email protected]
Chad Elmore Managing Editor Tel: +1 262 754 4114 E-mail: [email protected]
Josh Kunz Power Progress Brand Manager Tel: +1 414 379 2672 E-mail: [email protected]
Roberta Prandi Power Progress International Brand Manager Tel: +39 334 6538183 E-mail: [email protected]
Simon Kelly Sales Manager Tel: +44 (0) 1892 786 223 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA